All units have now been reserved and progress on site is going well as we edge closer to completing work across all the units:

  • Fencing erected between Plots 8 & 9 with steps to Plot 8 blockwork also completed
  • Decorations well underway to Plot 7 (last plot to be decorated) and garden topsoiled
  • Timber sleeper retaining wall completed to Plots 5 & 6 and retaining wall to Plot 6 complete
  • Alternative brickwork supplier sourced for remaining bricks and order placed