• Existing roof finishes have been completely removed with new felt and batten installation underway.
  • Barge & fascia boards have been installed to existing roof structure with decoration underway.
  • Removal of all existing rafters nears completion in preparation for raising the central roof area.
  • The chimney stack is being dismantled
  • Boarding of the ground floor joists has taken place to the annex off the main building.