117 Newbridge Hill – progress report

Progress Update for week 58: Floor finishes completed to second floor. First two units now ready for snagging Decorations nearly complete on first floor Gloss painting completed on first floor Scaffold erected in stairwell to allow high level boarding and decorations to commence Tiling in progress on first floor...

Read More

117 Newbridge Hill – progress report

Progress Update for Week 50: Second fix carpentry underway on second floor Second fix mechanical nearly complete on second floor Plastering remains in progress on first floor Decorations started on first floor Boarding of walls and ceiling to ground floor in progress Install of external retaining walls complete New...

Read More