Work continues on site with the following key areas of progress for project week 39:

  • The scaffolding roof has successfully been removed.
  • Stoning up to level in the basement continues.
  • Mechanical installations continue with waste stacks installed down to basement and gas pipework within the communal staircase.
  • Installation of fire boarding continues where available
  • Fixing of battens to ceilings for boarding progressed down to Ground Floor.
  • Fire stopping continues on first floor where possible.